ProjectsNOC NLQ ProjectHQFP-8

NOC NLQ Project

Local sourcing & budgetary RFQ · Qatar · 2026

Project health

Local sourcing is on track

Ten packages are moving through structured sourcing. Three quotations are ready for technical and commercial review.

44%Progress

5 sourcing

4 evaluating

1 delivered

Timeline

Planned campaign schedule

Package
Sep 01Sep 15Oct 01Oct 15
P01 10,000 BHP Main Tug
Evaluation
P02 5,000 BHP ASD Tugboats
Sourcing
P03 300-ft Assembly Barge
Sourcing
P04 Supply Vessel
Delivered
P05 Survey & Positioning Subcontract
Evaluation
P06 ROV Subcontract
Sourcing
Deliverables108 active · 1 delivered
quotes32 need commercial review
Follow-ups4Next due Aug 28

Recent activity

A

Anna Quotation received from Halul Offshore14 min ago

C

CYS Project Team Commented on P05 survey packageYesterday

Y

Yang Dalu Updated P04 to deliveredAug 25